Project

Kaweah Flume

Kaweah Flume
Client
Southern California Edison
Location
Visalia, CA
Start Date
12/18/2021
Date of Completion
03/30/2022
Overview

A large portion of the Kaweah Flume was damaged during a rockslide.  SR Diversified was contracted to analyze alternatives in the design, lifecycle costs, and schedule implications.  The findings of the investigation ultimately resulted in flume footing demolition and replacement of the entire structure. Challenges on this project included a remote location with steep and unstable terrain. SR Diversified was able to mitigate the risks and challenges on this project by implementing the use of helicopters for material delivery, providing regular training for safety hazards, and partnering with the owner’s air operations and safety team for coordination and best practices.